<aside> ❗ All red requirements are Optional, according to the 20% scope limitation defined by the professors.

</aside>

<aside> ⚠️ All yellow requirements will be dropped out if 1 or 2 group members drop out of the project, according to our risk mitigation plans of the risks 19 and 20.

</aside>

Project Schedule

NE-117Planning and Documentation (TOTAL)
NE-41Design arm support
NE-44Design wiring
NE-121Software
NE-100Design app flowchart
NE-99Design sequence diagram
NE-118Front-End
NE-102Research where to deploy web app
NE-98Design use case diagram
NE-69Create frontend code repository
NE-81Start react app
NE-90Develop API communication
NE-95Develop instructions before session
NE-94Develop session interface
NE-96Develop on-going session interface
NE-97Develop patient's listing
NE-93Develop session access control
NE-101Deploy web app
NE-91Develop session data acquisition
NE-92Develop session history interface
NE-87Develop login mechanism
NE-86Develop bluetooth protocol/communication
NE-89Implement register new session by health professional
NE-88Implement patient registering by health professiona
NE-83Design patient's app interface prototypes
NE-82Design health professional app interface prototypes
NE-85Develop health professional's app interface
NE-84Develop patient's app interface
NE-119Back-End
NE-70Design database (ER diagram)
NE-73Create database
NE-74Create API repositories
NE-68Create backend code repository
NE-72Develop API
NE-75Setup cloud environment
NE-80Create endpoints of patient
NE-79Create endpoints of health professional
NE-77Develop API services
NE-76Deploy services to cloud
NE-71Develop authentication system
NE-78Cloud server research
NE-115Integration
NE-109Integrate firmware and front-end
NE-108Integrate electronics and mechanics
NE-107Integrate firmware and electronics
NE-110Integrate front-end and back-end
NE-112Final tests
NE-111Final integration
D1: design da eletronica sep. 28th
D2: finalização da eletronica e inicio do design da mecanica oct. 05th
D3: finalizaçao da mecanica e integração da mecanica e oct. 19th
D4: Software project oct. 26th
D5: Mechanics,
hardware and software integration nov. 09th
D6: Overall integration and
functional tests nov. 16th